Model Readiness Reporting Schedule

Reporting a regulator can attach to the approval of a major capital project, so the path to the in-service date can be seen during construction.

The question a regulator faces

A regulator approves a major capital investment on the basis of a cost, a schedule and an in-service date. Customers begin to pay for the asset when it enters service, or bear the cost of delay when it does not. During construction the regulator usually receives reports on expenditure and progress. It rarely receives evidence of whether the asset, and the utility that will run it, will be able to energize, commission and operate it on the date approved.

Whether the spending was prudent is then reviewed after the money has been spent. The same question can be examined during construction, with evidence, while there is still time to act. ICxA calls that subject readiness.

What readiness covers

Readiness is the condition in which sufficient evidence is available for a decision to proceed. It applies at every point of commitment in a project, not only at the end: readiness to commit, to proceed, to integrate and to operate.

It covers the asset and its systems, which must be designed, procured, built, tested and integrated so that each system works with the others. It covers the organization that will operate the asset: its people, its organization, its care of the asset, and its systems and processes. It also covers the interfaces and contracts between the parties, and the evidence and governance on which each decision rests.

What the schedule contains

The schedule lists eleven reports in four parts. A regulator selects the ones that suit the project.

  1. With the application or at approval. A readiness baseline, a readiness maturity plan with dated milestones, the governance of readiness decisions, and the operating outcomes reconciled to the application.
  2. During procurement and construction. A periodic readiness report, a report at each milestone, and notice of material change.
  3. At commissioning and entry into service. Evidence that each critical system is ready before it is energized, that the operating organization is ready before start-up, and the record of each transfer to the operator.
  4. After the in-service date. Performance over the stabilization period against the ramp-up assumed in the application.

How it works

The utility reports evidence, and the regulator or a reviewer it appoints forms its own view. The reporting follows the stage-gates and readiness conditions the project itself has defined under the ICxA Standards. A low level of readiness early in a project is expected; the reports show whether it is maturing when the project’s own plan requires. Any consequence of a report, including for cost recovery, is the regulator’s decision under its own powers.

The schedule shares its basis with the Lender Readiness Implementation Pack, so a utility that also reports to lenders produces its readiness evidence once.

Terms of use for public bodies

Public bodies acting in an oversight role, including regulators, audit offices, parliamentary committees and government project assurance bodies, may use, cite and reproduce this schedule without charge and without ICxA membership, with attribution to the Institute of Commissioning & Assurance. ICxA membership is required to state publicly that an organization, service or assessment is aligned with the ICxA Standards, to hold ICxA credentials, and to use this material in a commercial service.

Next steps

The Missing Measure

A short brief on why scope, schedule and budget do not show whether an asset will operate.

Access the ICxA Standards

The free Corporate Preview membership gives your organization the Standards in full. No card and no expiry.

Talk to ICxA

Ask about the schedule, or arrange a briefing for regulatory staff.