Readiness Audit Criteria

Criteria a public auditor can use to examine whether a major capital project will be able to enter service and operate as intended.

The question behind value for money

A performance audit tests value for money against criteria. For a major capital project, cost, time and scope have accepted criteria. Whether the asset can be brought into service and operated as intended usually does not. It is examined after the fact, when a project has already entered service late or below its planned performance, and the finding is often the same: the asset was built, but it was not ready.

ICxA calls that subject readiness. These criteria let an auditor examine it while the project is still being delivered.

What readiness covers

Readiness is the condition in which sufficient evidence is available for a decision to proceed. It applies at every point of commitment in a project, not only at the end: readiness to commit, to proceed, to integrate and to operate.

It covers the asset and its systems, which must be designed, procured, built, tested and integrated so that each system works with the others. It covers the organization that will operate the asset: its people, its organization, its care of the asset, and its systems and processes. It also covers the interfaces and contracts between the parties, and the evidence and governance on which each decision rests.

What the criteria contain

There are 28 criteria in six areas. Each states what should be in place, the evidence to examine, and the clauses of the ICxA Standards it rests on.

  1. Outcomes and commitment
  2. Contracts, interfaces and decision authority
  3. The asset and its systems
  4. The operating organization
  5. Evidence
  6. Risk, deferred work and correction

How an auditor can use them

What can be expected depends on where the project is in its life. Before the investment decision and through engineering, the criteria test whether a credible path exists. During procurement and construction, they test whether the asset, its systems and the operating organization are progressing when the project’s own plan requires. From commissioning to operations, they test whether the conditions for each start-up and each transfer have been demonstrated.

A low level of readiness early in a project is normal. The risk is the absence of evidence that it is maturing. The criteria describe evidence. They do not certify that a project is ready, and the auditor forms its own conclusion.

Terms of use for public bodies

Public bodies acting in an oversight role, including audit offices, regulators, parliamentary committees and government project assurance bodies, may use, cite and reproduce these criteria without charge and without ICxA membership, with attribution to the Institute of Commissioning & Assurance. ICxA membership is required to state publicly that an organization, service or assessment is aligned with the ICxA Standards, to hold ICxA credentials, and to use this material in a commercial service.

Next steps

The Missing Measure

A short brief on why scope, schedule and budget do not show whether an asset will operate.

Access the ICxA Standards

The free Corporate Preview membership gives your organization the Standards in full. No card and no expiry.

Talk to ICxA

Ask about the criteria, or arrange a briefing for your audit team.